Log in
Prospector Park

Bid approved for Apache Junction drainage improvements

Posted

A nearly $360,000 bid for Prospector Park drainage improvements was approved recently by the Apache Junction City Council.

The council on Feb. 18 voted unanimously as part of a consent agenda with other items to approve the contract with Primary Construction Inc. not to exceed $359,952.73 which includes a 5% contingency.

Seven bids received for planned Prospector Park drainage channel improvements were rejected late last year because they were above the city of Apache Junction’s budget for the work. The Apache Junction City Council voted unanimously Dec. 17 to reject proposals received for work at the park, 3015 N. Idaho Road.

On Dec. 30 the city reissued a request for bids for the park’s drainage improvements and on Jan. 15 the city received four responses, Parks and Recreation Director Liz Langenbach said in a memo to the council.

They were:

  • Combs Construction Co. Inc., $747,124.
  • Scholz Contracting LLC, $450,304.
  • Bider Neve LLC, $343,484.
  • Primary Construction Inc., $342,812.12.

“Because Primary Construction Inc. was the lowest, responsive bidder, staff recommend awarding contract for the base bid amount listed above plus 5% contingency for a total of $359,952.73,” she wrote in the memo. “The budget for this project was $300,000; however, the department has other savings to accommodate the increase for this critical project.”

Richard H. Dyer can be reached at rdyer@iniusa.org, or on X @rhdyer. To voice your opinion on this story, connect with us at AzOpinions@iniusa.org.

Apache Junction, park, bid, contract

Share with others


Have an opinion on this story? Click here to send a letter to our editors.

Comments

No comments on this item Please log in to comment by clicking here