The Apache Junction Water District will pay a company $2.7 million for construction administration and inspection services for the expansion of the district’s water treatment plant to 10 million gallons per day.

The Apache Junction Water District board, comprised of Apache Junction City Council members, voted unanimously on Oct. 21 to approve a $2,735,475 professional service agreement between the water utilities community facilities district and Wilson Engineers LLC for Phase 3 final build out of Superstition Area Water Plant construction administration and inspection services.

The district needs a consultant to do the construction administration and inspection services as it expands its water treatment plant to 10 million gallons per day. That expansion will cost an estimated $60 million, Water District Director Mike Loggins said prior to the vote.

“As you are aware, we have a large development going on to the south. We completed our first phase of our expansion of our surface water treatment plant recently. It’s going from 2 million gallons per day to 4 million gallons a day. This next step is going from that four million gallons a day to 10 million gallons a day — our ultimate buildout of this site,” he said.

“This will be a pass-through cost for us that the developer is paying because he’s paying for the production of that plant to upsize it, to do the expansion for us. So we’re recommending using Wilson Engineers under the Scottsdale engineering service contract — it’s a cooperative agreement,” Loggins said.

Water district

The Apache Junction water district supplies well water (groundwater) pumped from the Eastern Salt River Sub-Basin Aquifer, which flows southwesterly under Apache Junction and its surrounding areas. The groundwater is treated for arsenic removal where necessary, disinfected with chlorine, pumped into storage tanks and blended with Colorado River (surface) water.

The surface water is transported through the Central Arizona Project canal system and filtered and purified at the Superstition Area Water Plant before being introduced into the distribution system.

The water district can also receive treated CAP water from the city of Mesa through an interconnect for a backup supply of water, if needed.

Richard H. Dyer can be reached at rdyer@iniusa.org, or on X @rhdyer. Please submit comments at yourvalley.net/letters or email them to AzOpinions@iniusa.org. We are committed to publishing a wide variety of reader opinions, as long as they meet our Civility Guidelines, https://www.yourvalley.net/civility-checklist/.