Higley Road water pipeline rehabilitation expected to restrict traffic
Valves along Higley Road will be closed the week of Dec. 15, which may impact households between Baseline Road and Williams Field Road, as well as Power Road to Val Vista Road, as shown on the map.
Courtesy Town of Gilbert
A four-month water pipeline rehabilitation project will begin Dec. 15 along Higley Road between Guadalupe Road and Ray Road, according to the town’s Public Works Department.
The project is intended to repair and restore aging pipes to extend their lifespan and reduce the need for costly replacements.
Valves along Higley Road will be closed during the week of Dec. 15, which may affect households between Baseline Road and Williams Field Road and between Power Road and Val Vista Road.
You must be a member to read this story.
Join our family of readers starting at $5 for your first month and support local, unbiased journalism.
Click here to see your options for becoming a subscriber.
Register to comment
Click here create a free account for posting comments.
Note that free accounts do not include access to premium content on this site.
I am anchor
Public works
Higley Road water pipeline rehabilitation expected to restrict traffic
Courtesy Town of Gilbert
Valves along Higley Road will be closed the week of Dec. 15, which may impact households between Baseline Road and Williams Field Road, as well as Power Road to Val Vista Road, as shown on the map.
A four-month water pipeline rehabilitation project will begin Dec. 15 along Higley Road between Guadalupe Road and Ray Road, according to the town’s Public Works Department.
The project is intended to repair and restore aging pipes to extend their lifespan and reduce the need for costly replacements.
Valves along Higley Road will be closed during the week of Dec. 15, which may affect households between Baseline Road and Williams Field Road and between Power Road and Val Vista Road.
Water service will not be interrupted, but water will be rerouted through other lines, which can cause temporary discoloration at taps. Officials said the water remains safe to use.
Town staff will flush the system to clear discoloration, which typically resolves within a few hours. Residents whose water remains discolored after several hours can call 480-503-6400 or submit a request through Gilbert 311 under the “Water – Quality (Brown Water)” category.
Brown water impacts are expected from Dec. 15 to Dec. 22 and again in April 2026.
Traffic restrictions will be in place for the duration of the project. Drivers can expect lane closures of up to two lanes in each direction and turn restrictions at intersections as needed.