Another Loop 202 Chandler exit to close for months
Starting June 12, eastbound exit at McQueen to shut down for 60 days
The eastbound Loop 202 (Santan Freeway) off-ramp at McQueen Road in the Chandler area will close for approximately 60 days starting at 11:30 p.m., Thursday, June 12.
Courtesy of Arizona Department of Transportation
The eastbound Loop 202 (Santan Freeway) off-ramp at McQueen Road in the Chandler area will close for approximately 60 days starting at 11:30 p.m., Thursday, June 12.
The closure will allow crews to reconstruct the ramp as part of the Arizona Department of Transportation’s Loop 202 widening project in the Southeast Valley.
The ramp is scheduled to reopen by mid-August. Drivers can detour by exiting eastbound Loop 202 at Arizona Avenue or Cooper Road while the off-ramp is closed.
You must be a member to read this story.
Join our family of readers starting at $5 for your first month and support local, unbiased journalism.
Click here to see your options for becoming a subscriber.
Register to comment
Click here create a free account for posting comments.
Note that free accounts do not include access to premium content on this site.
I am anchor
TRANSPORTATION
Another Loop 202 Chandler exit to close for months
Starting June 12, eastbound exit at McQueen to shut down for 60 days
Courtesy of Arizona Department of Transportation
The eastbound Loop 202 (Santan Freeway) off-ramp at McQueen Road in the Chandler area will close for approximately 60 days starting at 11:30 p.m., Thursday, June 12.
The eastbound Loop 202 (Santan Freeway) off-ramp at McQueen Road in the Chandler area will close for approximately 60 days starting at 11:30 p.m., Thursday, June 12.
The closure will allow crews to reconstruct the ramp as part of the Arizona Department of Transportation’s Loop 202 widening project in the Southeast Valley.
The ramp is scheduled to reopen by mid-August. Drivers can detour by exiting eastbound Loop 202 at Arizona Avenue or Cooper Road while the off-ramp is closed.
The $200 million Loop 202 Improvement Project is adding lanes and interchange improvements along eight miles of Loop 202 between Loop 101 (Price Freeway) and Val Vista Drive in Chandler and Gilbert.
This project is funded, in part, by Proposition 400, a dedicated half-cent sales tax that Maricopa County voters approved in 2004. The project is scheduled under the Regional Transportation Plan managed by the Maricopa Association of Governments, the metropolitan planning organization for the Greater Phoenix region.