Gilbert's North Water Treatment Plant project costs go up 

Finish also delayed a couple months as market construction challenges continue 

Posted

Construction inflation and market challenges are delaying the reconstruction and expansion of the Gilbert’s North Water Treatment Plant and driving its cost up, officials said. 

Project Manager Jeanne Jensen outlined what the project team has done to address those issues at the Gilbert town retreat Thursday, an annual meeting of council and staff that looks at important issues for the town to address in the coming year. 

The plant’s cost now projects to be $545 million and completion is anticipated for end of February 2026. The town broke ground on the project in March. Original cost projections were for $457 million in construction  

The plant, which treats water from the Salt River Project watershed and groundwater, serves about 150,000 people in town. It treats about 45 million gallons per day. At build-out, it expects to serve about 250,000 people, part of the reason the town believed it necessary to expand its treatment capacity to 60 million gallons per day. 

The additional capacity will also help the town with its resiliency plan as the region deals with water shortages along the Colorado River. 

Jensen reviewed how the town has reviewed its construction schedule and plans and then squeezed out further efficiencies in plans to save money and time. 

Jensen said paying for the additional costs in the project will involve shuffling and delaying some capital improvement projects and possibly looking at rates in the future. 

No formal action is taken at retreats and staff did not ask for additional direction from council on the item. 

town of Gilbert, North Water Treatment Plant, Jeanne Jensen

Share with others


Have an opinion on this story? Click here to send a letter to our editors.

Comments

No comments on this item Please log in to comment by clicking here