The second phase of replacing air-lift pumps that move sludge at the Apache Junction water reclamation facility with mechanical pumps will cost $575,000.
The Apache Junction Sewer District Board voted unanimously Sept. 23 to purchase and replace three return-activated sludge pumps for clarifier Nos. 1 through 3 at a cost not to exceed $575,000 to be paid from the Capital and Replacement Fund.
When activated sludge enters rectangular clarifiers at the water reclamation facility, it settles by gravity to the bottom and the remaining clarified water is decanted from the surface. Settled sludge is removed and sent to aeration basins as return activated sludge, it states in a district document.