Current print subscribers can create a free account by clicking here
Otherwise, follow the link below to join.
To Our Valued Readers –
Visitors to our website will be limited to five stories per month unless they opt to subscribe. The five stories do not include our exclusive content written by our journalists.
For $6.99, less than 20 cents a day, digital subscribers will receive unlimited access to YourValley.net, including exclusive content from our newsroom and access to our Daily Independent e-edition.
Our commitment to balanced, fair reporting and local coverage provides insight and perspective not found anywhere else.
Your financial commitment will help to preserve the kind of honest journalism produced by our reporters and editors. We trust you agree that independent journalism is an essential component of our democracy. Please click here to subscribe.
Need to set up your free e-Newspaper all-access account? click here.
Non-subscribers
Click here to see your options for becoming a subscriber.
Register to comment
Click here create a free account for posting comments.
Note that free accounts do not include access to premium content on this site.
I am anchor
Transportation
Ocotillo widening project underway in Queen Creek
Posted
Ocotillo Road, the east-west route through the heart of Queen Creek, is being widened from Ironwood to Signal Butte roads.
The project includes widening Ocotillo Road to two lanes in each direction with center turn lanes, bike lanes, sidewalks, drainage improvements, utility modifications and intersection enhancements at Meridian Road and Barnes Parkway.
The project also will widen Meridian Road south to two lanes in each direction, connecting to the previously widened road.
Improvements are anticipated to be complete in late 2022.
“This project is another example of our commitment to ‘Better Roads Ahead’ in Queen Creek,” said Queen Creek Mayor Gail Barney in a press release. “With the completion of this project, Ocotillo Road will be two lanes in each direction from Ironwood all the way to Hawes. The project is being completed with support from Maricopa County and W Holdings. We know roadway improvements can be inconvenient and we appreciate the community’s continued patience while we make these important infrastructure improvements.”
Roadway projects under construction:
Queen Creek and Signal Butte
Chandler Heights and Power
Another major road project under construction is the extension of State Route 24, which will provide two lanes in each direction from Ellsworth to Ironwood. The Arizona Department of Transportation project will provide major relief for Queen Creek and the region. The interim road will include access ramps at Williams Field, Signal Butte, Meridian and Ironwood. It is anticipated to be complete in fall 2022. For more information, visit QueenCreekAZ.gov/SR24.
Road projects in design, nearing construction:
Meridian – Queen Creek to Germann
Meridian – Cherrywood to Combs (phase 2)
Queen Creek – Ellsworth to Crismon
The Town is halfway through the 10-year infrastructure improvement plan. Since 2016, the following major road improvements have been completed:
Rittenhouse - Sossaman to QC Marketplace
Sossaman and Chandler Heights intersection improvements
Ocotillo - Power to Recker
Ocotillo - Rittenhouse to 218th Pl
Ocotillo - Heritage Loop to Ellsworth Loop
Ellsworth - Ocotillo to Rittenhouse
Ellsworth - Queen Creek to Germann
Crismon - Queen Creek to Germann
Power - Ocotillo to Brooks Farm
Riggs - Power to Meridian
Meridian - Cherrywood to Combs
Germann - Meridian to Ironwood
Rittenhouse – 213th to Riggs
As road improvements continue, town officials encourage drivers to slow down, allow extra time for travel and be courteous of motorists and work crews. To receive weekly traffic alerts, sign up for eNotifications on the Town’s website.