Town Hall parking lot closures phased June 14-19

See map for available parking spaces

Posted 6/14/24

The Town Hall parking lot will see incremental closures starting Friday, June 14 to allow for work on the parking lot surface.

Milling schedule:

June 14: The red area pictured will be …

You must be a member to read this story.

Join our family of readers for as little as $5 per month and support local, unbiased journalism.


Already have an account? Log in to continue.

Current print subscribers can create a free account by clicking here

Otherwise, follow the link below to join.

To Our Valued Readers –

Visitors to our website will be limited to five stories per month unless they opt to subscribe. The five stories do not include our exclusive content written by our journalists.

For $6.99, less than 20 cents a day, digital subscribers will receive unlimited access to YourValley.net, including exclusive content from our newsroom and access to our Daily Independent e-edition.

Our commitment to balanced, fair reporting and local coverage provides insight and perspective not found anywhere else.

Your financial commitment will help to preserve the kind of honest journalism produced by our reporters and editors. We trust you agree that independent journalism is an essential component of our democracy. Please click here to subscribe.

Sincerely,
Charlene Bisson, Publisher, Independent Newsmedia

Please log in to continue

Log in
I am anchor
construction

Town Hall parking lot closures phased June 14-19

See map for available parking spaces

Posted

The Town Hall parking lot will see incremental closures starting Friday, June 14 to allow for work on the parking lot surface.

Milling schedule:

June 14: The red area pictured will be closed off and the Lincoln Drive entrance will be closed during construction (6 a.m. to 5 p.m.). Parking will only be available in the blue area.

June 15: The blue area pictured will be closed off and the Invergordon entrance will be closed during construction (6 am to 5 pm). Parking will only be available in the red area.

Paving schedule:

June 17: The green area pictured will be closed off and the Lincoln Drive entrance will be closed during construction (6 am to 5 pm). Parking will be available in yellow and orange areas.

June 18: The orange area pictured will be closed off and the Invergordon entrance will be closed during construction (6 am to 5 pm). Parking will be available in green and yellow areas.

June 19: The yellow area pictured will be closed off on this day. Both entrances to the Town hall campus will be open. Parking will be available in the green and orange areas.