Opinions

Rubberized asphalt removal: Interstate 10 Broadway Curve reconstruction under way

Posted 8/3/21

It’s go time! If you’ve noticed things are starting to look a little different on Interstate 10 in the Southeast Valley, you’re not alone. Crews have started the first phase of work …

To Our Valued Readers –

Visitors to our website will be limited to five stories per month unless they opt to subscribe. The five stories do not include our exclusive content written by our journalists.

For $5.99, less than 20 cents a day, digital subscribers will receive unlimited access to YourValley.net, including exclusive content from our newsroom and access to our Daily Independent e-edition.

Our commitment to balanced, fair reporting and local coverage provides insight and perspective not found anywhere else.

Your financial commitment will help to preserve the kind of honest journalism produced by our reporters and editors. We trust you agree that independent journalism is an essential component of our democracy. Please click here to subscribe.

Sincerely,
Charlene Bisson, Publisher, Independent Newsmedia

Please log in to continue

Log in
I am anchor
Opinions

Rubberized asphalt removal: Interstate 10 Broadway Curve reconstruction under way

Posted

It’s go time! If you’ve noticed things are starting to look a little different on Interstate 10 in the Southeast Valley, you’re not alone. Crews have started the first phase of work to remove rubberized asphalt from the roadway.

The process is the first step in more than three years of major reconstruction work on one of the busiest sections of interstate freeway in Arizona, and it’s all part of the I-10 Broadway Curve Improvement Project.

Crews with Broadway Curve Constructors kicked off the project on July 23 with the removal of one inch of rubberized asphalt along approximately five miles of westbound I-10 between Loop 202 and U.S. 60 (Superstition Freeway).

During the first closure of westbound I-10, five milling machines got to work grinding off the top layer of rubberized asphalt, creating 13,500 tons of material and filling 575 truckloads. Much of that material will be recycled.

Similar removal work is scheduled on I-10 over weekends through September. You can find closure and detour information on the project website at azdot.gov.

Removing the top layer of rubberized asphalt is important so construction crews can establish their work zones and shift the travel lanes as required throughout construction. For a project of this size and scope, we anticipate dozens of work zone and travel lane shifts.

With the application and removal of temporary lane striping for each change, this would create significant wear and tear on the pavement surfaces. Also, when the rubberized asphalt is taken off, workers can inspect the concrete pavement and repair areas that are cracking or beginning to break.

Drivers might notice that I-10 looks different after the rubberized asphalt has been removed. The payoff will come at project completion, when a safer, wider and more efficient highway will be ready for the approximately 300,000 drivers who take the route every day.

Editor’s note: This update was provided by officials at the Arizona Department of Transportation. Visit azdot.gov.